Community Updates

We’re excited to keep you informed on the progress of our new Cantiro townhomes in Arbour Lake West! This dedicated space is designed to access monthly updates, construction milestones, and important information about your future home in the vibrant Arbour Lake West community. Stay connected with us as we work diligently to bring your dream home to life. Thank you for being a part of this journey with Cantiro Homes!

  • Building 1

    The foundation for Building 1 is complete, inspections have passed, and backfilling is now underway! Things are moving forward smoothly.

    Building 8

    The foundation wall pour for Building 8 is now underway. Progress is moving forward as scheduled.

    Building 9

    The foundation for Building 9 is complete, inspections have passed, and backfilling is now in progress! We’re making great strides!

    Building 10

    Building 10 is progressing well— the foundation is complete, inspections have been passed, and backfilling is now underway. Things are moving along as planned.

  • December 3

    The concrete for Building 1 has been successfully poured, marking an exciting milestone in its construction. This critical step ensures a strong and stable foundation for everything to come. We’re thrilled to see this project taking shape, one step closer to completion!

    December 3

    Building 9 has reached a major milestone with the concrete foundation now in place. This foundational work is essential to creating a durable and long-lasting structure. With this step completed, we’re eager to move forward with the next stages of construction.

    December 3

    Concrete has been poured for Building 10, solidifying its foundation and setting the stage for future progress. A strong foundation is key to any successful build, and we’re proud to achieve this milestone. Stay tuned as we continue bringing Building 10 to life!

     

  • November 15

    • Site Paving: The paving on site has been completed.

    November 20

    • Foundations: Digging has begun for the foundations on building 1, 8, 9, and 10.
    • Excavation: Buildings 1, 9, and 10 fully excavated with building 8 half way complete

    November 25

    • Form Work: Form work for footings installed and inspections passed for buildings 1 and 10.

    November 28

    • Development Permit: We are excited to announce our development permit was released on November 28.
    • Project Touchpoint: Sales Manager (Leah Turner) will be reaching out to book a meeting with purchasers to share electrical layouts and answer any questions.
  • October 2024

    • Development Permit: We are pleased to announce that the Development Permit was approved with conditions on October 8, 2024. If you would like more information about this process, please visit here.
    • Site Servicing: The site servicing is now complete, marking a significant step forward in our development process.
    • Excavation: Excavation work is set to commence in November, bringing us closer to the construction of your new townhome.