We’re excited to keep you informed on the progress of our new Cantiro townhomes in Arbour Lake West! This dedicated space is designed to access monthly updates, construction milestones, and important information about your future home in the vibrant Arbour Lake West community. Stay connected with us as we work diligently to bring your dream home to life. Thank you for being a part of this journey with Cantiro Homes!

  • November 15

    • Site Paving: The paving on site has been completed.

    November 20

    • Foundations: Digging has begun for the foundations on building 1, 8, 9, and 10.
    • Excavation: Buildings 1, 9, and 10 fully excavated with building 8 half way complete

    November 25

    • Form Work: Form work for footings installed and inspections passed for buildings 1 and 10.

    November 28

    • Development Permit: We are excited to announce our development permit was released on November 28.
    • Project Touchpoint: Sales Manager (Leah Turner) will be reaching out to book a meeting with purchasers to share electrical layouts and answer any questions.
  • October 2024

    • Development Permit: We are pleased to announce that the Development Permit was approved with conditions on October 8, 2024. If you would like more information about this process, please visit here.
    • Site Servicing: The site servicing is now complete, marking a significant step forward in our development process.
    • Excavation: Excavation work is set to commence in November, bringing us closer to the construction of your new townhome.